Page 1 of 49

Transactions on Engineering and Computing Sciences - Vol. 12, No. 1

Publication Date: February 25, 2024

DOI:10.14738/tecs.121.16260.

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the

Perspective of the New Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and

Computing Sciences, 12(1). 54-102.

Services for Science and Education – United Kingdom

Risk Allocation and Sharing in Mega Industrial Projects from the

Perspective of the New YellowBook -FIDIC-2017 to Approach a

Balanced Construction Contract

Ahmed Mohammed Abdelalim

ORCID:(0000-0003-3359-715X)

Faculty of Engineering at Mataria,

Helwan University, Cairo, Egypt

Mona Abdelhamid Hassanen

Faculty of Engineering at Mataria, Helwan University

Adel ElSamadony

Faculty of Engineering at Mataria, Helwan University

ABSTRACT

Owners frequently allocate excessive risks to contractors and utilize (custom)

contracts to fit their project needs and specifications. The MENA region has seen a

boom in industrial projects in recent years, which has made it imperative to

examine the barriers to optimal risk allocation and throw light on the processes

currently in place for risk allocation. In order to approach a balanced construction

contract, the current article aims to investigate the existing risk distribution in

mega industrial projects. Properly identifying, evaluating, and assigning risks in

contracts can improve project performance. First, the study found 70 risk factors

that were categorized into nine groups based on a thorough literature review and

scientometric analysis. Estimates of the likelihood, impact, and method of control

for these risk factors were requested from the respondents. The findings showed

that the way risk is now allocated in construction projects is ineffective and has

resulted in a number of other issues, including aggressive contractual relationships,

claims, and conflicts. Strong organizations today work hard to maintain effective

partnerships by enforcing policies that promote cooperation and aid in risk

management. Contractual provisions used in mega industrial projects become less

flexible and less able to accommodate the needs and interests of the parties

involved in all potential situations as a result of standardization. One of the most

prominent standard forms of contracts for mega industrial projects, the Conditions

of Contract for Plant and Design Build (FIDIC form 2017 Yellow Book), was

researched and reviewed to identify risky provisions and offer solutions for

contractual issues. In order to reduce the project's major risk factors and partially

reform the contract requirements into risk-balanced conditions that may improve

the contract's utility as a project management tool, several modifications were

made. These amendments concentrated on the particular needs of mega industrial

projects and made a concerted effort to address a numberof issues, including the

Employer and Contractor's responsibility matrix, liability limitations, resolving

procurement-related issues, design errors and contradictions in documents, the

Page 2 of 49

55

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

necessity of coordination between contractors and subcontractors, the significance

of following the project schedule, and the relationship between delay damages and

project milestones. Contract parties will benefit from the study's findings in terms

of effective project management, risk reallocation, management, and reduction of

claims, as well as preventing disputes.

Keywords: Mega Industrial Projects, Risk allocation, Relative Importance Index,

Frequency-Adjusted Frequency Index, Risk identification,optimal risk, risk management,

FIDIC-2017 Yellow Book, Delay Damages.

INTRODUCTION

Project management units face more obstacles and hurdles as a result of the pressing need to

implement mega industrial projects in the MENA area. The complexity of mega industrial

projects is growing, which causes hazards that are typical in these projects to become more

severe and frequent (Youssef, A., et al., 2018; Abdelalim, A.M., et al., 2022, 2023). These

complexities necessitate clear definitions of the rights and obligations of contracting parties.

Since risk is a constant in industrial projects, effective management has the potential to boost

earnings and provide businesses a competitive edge.

In the construction sector, a number of researchers carried out risk assessment studies in a

variety of global locations, such as the US, Europe, and East Asia. Nevertheless, there is a dearth

of such research in the Middle Eastern construction sector (Eskander, et al, 2018). It is unjust

and irrational to transfer the unmitigated risks of construction project to one party; in the past,

this has led to adversarial relationships between contractual parties and increased claims and

disputes. Despite the fact that a large number of significant studies on construction risk in

industrial projects have been carried out, a number of research gaps remain unfilled (Hanna, et

al 2013). Every study that is now available offers a portion of the answer, but the construction

sector still requires a fully accepted multiparty, non-unilateral risk allocation sustainable

model. There is a broad consensus among academics and industry professionals in favor of an

owner-contractor collaborative partnership. Over the past few decades, many studies have

been conducted on the distribution of construction risks (Zhang, L., et al, 2017). Industry

players continue to express anxiety about the risk associated with mega projects, despite the

fact that the research that is currently available provides some helpful insights into the issue.

A number of working relationships, communications, and contractual duties are not being

carried out in good faith and in a transparent manner, which has led to a strain in contract

relationships in the industrial projects of the MENA region in recent years (Abdelalim, A.M., et

al., 2018, 2019, and 2020). M. Marzouk (2011 Researchers and practitioners are generally in

favor of a cooperative connection between the owner and the contractor (Zhang, S., et al, 2016).

Assaad et al. (2020b) found thatcertain risks can be appropriately managed by sharing them

between the two contracting parties rather than allocating them to a single party. In this

instance, the general terms of a contract between project parties usually contain various

construction risk clauses. According to Hannaet al. (2013), there will always be risk involved in

industrial projects, even with improved knowledge of those hazards and a sound risk

distribution strategy. But by structuring construction contract language correctly, risk can be

distributed and many of the unclear and illegal arguments can be minimized. However, contract

standards are becoming more stringent with an increasing number of new contract types in an

Page 3 of 49

56

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

effort to mitigate risks during project implementation. The important risk considerations for

design-build projects in the constructionsector are discussed in this study. An ad hoc contract

based on the design-build contract type can be used by owners and contractors with greater

confidence if these risk elements are properly identified, allocated, and managed. Although

contracts are essential business assets, construction projects are vulnerable to future

uncertainties due to their inherent complexity, scope, and scale. According to Ramonu, JA, et

al.'s (2018) research on conflict types in the construction sector, contractual disagreements

rank as the most significant and common type of disputes in construction projects. The

economic and administrative issues, however, were dealt with last. Thus, categorizing disputes

has given rise to a basis for avoiding confrontations in construction projects. Contract

conditions typically serve a crucial regulatory role in all project interactions between the

various project parties, making them an important tool for managing construction risks.

Numerous researches indicate that if contract terms are not appropriately taken into account,

they could end up becoming one of the most significant sources of risks in construction projects.

Since risk is a constant in the construction sector, effective risk management can boost earnings

and strengthena company's competitive edge, Suprapto, M., Abdelalim, A.M. and others 2016

and 2017. It is crucial to concentrate on existing risk allocation practices and research the

barriers to ideal risk allocation in Mega industrial projects given the growth in construction

projects expected in the MENA area in the next years. In order to share the future loss of

opportunities or project advantages proportionately, contractdrafting is therefore crucial to

successful contract management, where balanced risk allocation specifies and distributes risk- related obligation. As a result, maintaining the balance of risk allocation has emerged as a

critical component of successful project management which helps to ensure the balance of

liabilities and gains among project parties.

The distribution of construction risk among the project's stakeholders (owner, designer,

contractor, etc.) greatly affects the project's overall objective (see Figs. 1, 2). As a result, risk

distribution has garnered a lot of attention in recent years as a crucial component of contractual

governance for building projects (see Tables 1, 2). The main project participants—owners,

engineers, contractors, and material suppliers are obligated by both direct and indirect

contractual agreements; yet, their interests in the project may differ, and they may assess the

risks and their allocations differently. According to some academics, this uneven distribution of

risks will force the contractor to use defensive tactics, such as lowering the quality of their work

or inflating their invoices (Nasirzadeh, F., et al., (2014). Inappropriate risk allocation has

resulted in violent interactions between contract participants since it can have a substantial

impact on the behavior of project participants. On the other hand, risk allocation in construction

projects is typically not evenly distributed. Strong businesses today make the effort to ensure

that they maintain fruitful partnerships by implementing policies that promote cooperation

and aid in risk management. Nevertheless, the advantages of sound contracting are often

overlooked because those who draft and negotiate them have a propensity to prioritize

avoidance over appropriate risk allocation. This highlights how crucial it is to assess

conventional contract terms, particularly those that address how incorrect risk distribution can

lead to antagonistic interactions between contractual parties, T. Mellewigt et al. (2012).

Page 4 of 49

57

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

Fig.1: Hierarchy of Risk Classification (STEEP Risks of Megaprojects), in the micro level,

Boateng (2015), Zayed, (2008).

Table.1: Risk Allocation on Different Parties.

Risk Allocation Risk Description

Owner site access/right of way

differing site condition

delayed payment on contract

permits and ordinances

unidentified utilities

changes in work

acts of God

govt. acts and regulations and tax rate change

Page 5 of 49

58

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

Shared between all Parties contract-delay resolution

indemnification and hold harmless

financial failure-any party

third- party delays

change-order-negotiations

Design-Build contractor defective materials

actual quantities of work

quality of work

safety and accidents

contractor competence

establishment of a project costs

labor disputes

defective design

defensive engineering

Undecided weather conditions

environmental risks

inflation

redesign if over-budgets

Table.2: Risk Categorization according to importance.

Level of Importance Risk Description

Most important defective design

changes in work

differing site condition

delayed payment on contract

unidentified utilities

defective materials

financial failure-any party

Medium important actual quantities of work

weather conditions

safety and accidents

site access/right of way

defensive engineering

establishment of a project costs

redesign if over-budgets

environmental risks

quality of work

change-order-negotiations

permits and ordinances

third- party delays

indemnification and hold harmless

contractor competence contract-delay resolution

Least important inflation

labor disputes

govt. acts and regulations and tax rate change

acts of God

Page 6 of 49

59

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

Fig.2: Hierarchical structure of criteria for the risk allocation

Although it's important to have different forms for construction contracts in order to

standardize contractual stipulations related to large-scaleindustrial projects, it can also be

helpful to offer revisions that improve the contract's risk-balance. Rather than winning a court

battle, thegoal of modifications to contracts is to make it easier for the parties to accomplish

project goals, respect contracting partners, and avoid disagreements. According to a number of

studies, contract terms can become major sources of risk in building projects if they are not

adequately taken into account Rameezdeen, R. et al.)2014(. Both the public and commercial

sectors in the MENA area have seen a notable increase in the use of design-build contracts as a

project delivery method. Nonetheless, unless the risks are sufficiently identified, evaluated, and

managed during the bidding and project execution stages, this project delivery method ends up

being risky for all contractual parties. The impact of the selected contract type and risk

management collaboration in construction projects was studied by Banik, G.C. (2008) and

Osipova, E. (2007). They discovered that the design-build project showed high project

performance and productive teamwork in risk management. From the contractor's point of

view, risk management works better in design-build projects since it allows the contractor to

have early project control.

Problem Statement

The investigation of the literature reveals that in significant industrial projects in the MENA

region, contractors and owners do not share sufficiently of the risks. The present study aims to

examine the risk variables associated with industrial projects in the Middle East and North

Africa (MENA) region, as indicated by Table 3. Additionally, the research will identify, evaluate,

and categorize the issues and roadblocks that impede the optimal allocation of risk in industrial

projects. Next, the important risk considerations for design-build projects in the construction

sector will be discussed in this article. Owners and contractors hoping to use the design- build contract will benefit fromeffective risk management of these aspects. Not only does the

research help identify and assess risk factors in mega industrial projects but also to better

Page 8 of 49

61

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

X26

X27

Engineer's satisfaction clauses

Perceived risks of dealing with a particular

engineer

X61 Miscommunication between the client & the

contractor

8

th Category: Risks related to Finance and Commercial

X62

X63

Interest rate changes

Limiting overdraft facilities

4

th Category: Risks related to the Project

X28 Defective materials

X29 New constructive methods that are

unfamiliar

X64 possible cash flow risks

X30 Availability of key inputs; labor, materials,

equipment

X65 Lack of full knowledge of taxes and duties

X31 Compliance risks (H&SE) X66 Client financial credentials

X32

X33

Force majeure

Using an unstudied design and methods

for the first time

X67 General market conditions

9

th Category: Legislations Risks

X68 Change in legislations/lows

X34 Design errors, omissions and

contradiction in documents

X69 Late issuance of licenses

X35 False progress reports X70 Delay due to statutory bodies

Research Objectives

Finding and analyzing important risk variables for large industrial projects in the MENA region

is the primary goal of this research. Secondly, creating a balanced construction contract that

aids in redistributing these risks to strengthen the bonds amongst the many project

participants. To do this, the risk factors affecting the project life cycle will be identified, and the

contract provisions pertaining to each risk will be examined and amended, or new clauses that

can reduce or remove risk factors will be added.

Creating and validating modifications to conventional contracts that the construction project

parties can utilize to more effectively allocate project risks is another important objective of

this research, which aims to improve the current risk allocation procedures in mega industrial

projects This study attempts to identify the risky contract clauses, as well as whether these

clauses expressly state the risks or if the risks are implicit in the clause itself, based on the risk

factors that were determined in the first section of a thorough investigation (see Table.3,

Hassanen, M., and Abdelalim, 2023). An inductive approach is used in the research, and general

contractual issues as well as the new standard FIDIC contract forms from 1999 and 2017

(Yellow Book) were studied.

A comparison is shown in Table 4. We then looked into therationale behind the changes and

recommendations made to this sample contract. Information is gathered for this using a

questionnaire survey and semi-structured interviews. The experts' response was a great asset

to the study because most of their risk-related solutions have already been developed and

applied to the creation of balanced construction contracts, which aim to solve the issues

preventing the best possible risk allocation within the specific construction sector. The findings

will suggest a few modifications to the sections of mega industrial projects' clauses including

the major risk elements.

Page 10 of 49

63

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

Scientometric Analysis of Risk Allocation and Sharing in Mega Industrial Projects

Research

The list of publications was extracted from the Web of Science Database (WoS). WoS was

chosen as the primary data source for the current study due to its widespread availability and

endorsement in extant literature, Zou, X., & Vu, H. L. (2019). The search strategy focused on

"risk allocation," examining titles, abstracts, and author-generated keywords. Data collection

concluded in 2023, covering the period from 2000 to mid-2023. After filtering non-English and

irrelevant publications, the authors retrieved 1355 documents regarding “Risk Allocation”,

4743 documents related to “Risk Identification”, 1376 documents related to “Optimal Risks”,

91 for “delay damages”. Despite that, the rarely found researches in contractual risks of Mega

Industrial Projects were emphasized by finding ONLY 3 papers discussed Mega Industrial projects

in light of FIDIC 2017, and Only 2 papers conducted in 2022 for claims and disputes according to

FIDIC 2017. The authors utilized keyword co-occurrence analysis to track the development of

"Risk allocation" studies. This method effectively visualizes evolving scientific trends and

subjects through graphical maps. Fig.3 visually represents these keywords, categorized into six

clusters. These clusters are color-coded as follows: purple indicates “Risk Allocation”, red

represents “PPP- Risks”, green corresponds to “Risk Identification”, and blue signifies for “other

mergers and acquisition processes that include risks”, yellow denotes “Risk Management” and

sky-blue stands. "Risk Allocation" serves as the central node, as shown in Fig. 3, with 507 links,

and total link strength of 2221. The second rank was for Risk Identification and Assessment,

with 271 links, and total link strength of 1582. “Risk management” was ranked the third of

investigated researches with 202 links, and total link strength of 1232.

Production of Publications per year

Page 12 of 49

65

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

Moreover, there is disagreement among those involved in construction projects over the best

approach for allocating risks. According to some academics, this uneven distribution of risks

will force the contractor to use defensive tactics, such as lowering the caliber of their work or

inflating their invoices, The field of risk management has seen an increase in interest in recent

years. Actually, risk management is crucialsince it raises a company's profitability, and not

doing so could have unfavorable effects, El-Adaway, I., 2020. Project risk management is

actually a procedure that entails locating sources of uncertainty; (risk identification),

estimating the likelihood and effects of uncertainties (risk analysis), developing strategies to

react to the risks examined (risk response), and finally tracking such risks and repeating such

steps across the project's life.

All construction projects must have a contract agreement since it outlines the parties'

responsibilities and the manner in which project expenditures are allocated. R.K. Kumar, 2019.

Construction contracts contain stipulations that help to reduce the inherent complexity of

industrial projects by allocating rights, obligations, responsibilities, and risks among the

parties. However, because contractual parties often prioritize risk avoidance above appropriate

risk allocation, excellent contracting benefits are frequently lost. Despite having both direct and

indirect contractual obligations, these parties might not share the same interest in the project

and might see the related risks and their distribution differently Standard construction

contracts (SFCs) are widely available, and their demonstrated benefits are one reason why

utilizing them is beneficial. However, recent studies and present practice indicate that owners

continue to rely on ad hoc (bespoke) or significantly amended SFCs. Youssef, A., and colleagues

(2018). Strong firms today work hard to ensure long-lasting, successful relationships by

incorporating clauses into contracts that promote cooperation and improve risk management.

The field of construction research is not new to managing and allocating risks. Researchers

from a variety of construction industry sectors have looked into the allocation and distribution

of risk in specific contract forms (Abdelalim, A.M. et al., 2020, 2021People tend to think of terms

like liability limitations, compensation, and the like when asked about contract terms that deal

with or are essential in controlling risks. Another common response is to mention clauses that

specifically refer to the word "risk," such as those that deal with the risks of the owner or

contractor in construction contracts or the risks of loss or damage in sales contracts. The

majority appear to believe that these are the sole clauses in the contract that address hazards.

Such an outlook would be excessively limited. Risks associated with contracts can come in a

variety of shapes and sizes. Studying past disputes and accusation experiences can help you

comprehend problematic terminology and worries and reduce the likelihood that something

will go wrong, Arditi, D. 2017. Risks associated with contracts can come in a variety of shapes

and sizes. Studying past disputes and accusation experiences can help you comprehend

problematic terminology and worries and reduce the likelihood that something will go wrong.

In their study, Li, H., and Arditi, D. (2017) postulated that by making sure the design is as

comprehensive as feasible; the owner can minimize project uncertainty and achieve good

project efficiency by being ready to cope with complexity. Alongwith encouraging healthy

competition between the contractor and subcontractors and the bidder, the owner should also

make sure that these parties participate in the project as soon as possible.

Page 13 of 49

66

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

Problems with Current Practice of Risk Allocation

Numerous construction projects fall short of their planned goals. Such a failure could be

explained in terms of severe project delays, cost overruns, and inefficient work. A key

contributing factor to such a failure is the existence of risks and uncertainties inherent in the

planning and implementation of projects. PMI, 2017. A five-phase risk management approach,

comprising risk identification, risk management strategy, qualitative and quantitative risk

analysis, and risk response planning, can help lessen the negative effects of defined risks. This

section looks at and assesses earlier studies to identify issues with current risk allocation

procedures in the construction industry, based on the examined literature. Tension, disputes,

and ineffective risk management appear to be related, Abdelalim, A.M, et.al 2016.

Time and Cost Overruns

Undervalued risks frequently result in monetary losses (Peckiene, A., 2013). Defensive risk

measures lead to poor quality and time and expense overruns. Thus, it is essential to distribute

risks fairly in order to achieve effective project performance protective tactics against risk.In

many developed and developing countries, the construction industry frequently faces delays

and cost overruns. Abdullah et al. (2018) discovered that the most important causes of delays

are poor/insufficient planning and scheduling, lack of subcontractor ability, and delays in

subcontractor work when identifying factors that lead to cost overruns and delays during

refinery projects for palm oil. Studies by Pham, L.H. et al. (2014) indicated that some delays

are caused by contractors, project owners, authorities, and external sources, (i.e., weather).

Therefore, the contractors need to increase their project management abilities in order to

extend the project's duration. In addition, the contractor's technical and managerial skills must

be carefully considered by the project owner while selecting the contractors. The project owner

must also establish a clear project scope, uphold the project requirements, and refrain from

making design changes throughout the fundamental design, also known as front-end

engineering design (FEED). (Adam, A., et al., 2015) came to the conclusion that the factors

causing cost overruns and time delays frequently overlap based on the body of research on the

causes of client cost overruns and delays in building projects. Consequently, two projects that

have the same underlying cause for a schedule delay or cost overrun could be interpreted quite

differently. Every explanation is distinct and depends on the research endeavour being

conducted.

Claims

Construction contracts are essential for averting the legal and administrative hazards that give

rise to claims, since the frequency of litigation involving construction projects has grown.

According to Mohammadi, S. (2016), the study aims to increase construction professionals'

awareness of these likely risks by identifying legal risk factors that could give rise to claims in

sustainable construction and by evaluating the criticality of each risk factor based on the

opinions of industry professionals and analysis using the relative importance index method.

Common reasons for claims were altered owner needs, additional labour, delays or

acceleration, different site circumstances, and unclear contracts, R. Komurlu et.al, 2017.

According to Dastyar, B., et al. (2018), the most significant variables influencing claims include

contractors' financial difficulties, shortage of materials, and high pricing when they provide a

contractual price below the required tender price. In construction projects, risk management

Page 14 of 49

67

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

is still largely ineffective. In their research, Haidar, A. (2011) provided a brief overview of this

issue. Their analysis indicates that undervaluation and imbalanced bidding are common causes

of claims. Many writers have researched the justifications for assertions. According to

Mohammadi, S. and Birgonul, M.T. (2016), contract-related problems are exacerbated by

irrational contract clauses as well as a lack of clarity in the contract agreements about payment,

modifications, and a performance time. As a result, as the project moves forward, additional

risks and unanticipated circumstances could surface, leading to potential disputes and a

breakdown of the relationship practices such as the use of performance bonds to shift the risk

of delays and cost overruns, dispute resolution processes to minimize litigation, and

negotiation tactics to prepare for litigation in the event of an unforeseen circumstance. Time

extensions, scope modifications, payment, administration, contractual duties, and other issues

are also included in disputes. They claim that one of the causes of disagreements is that the

party impacted did not acknowledge the risk as pertinent to the project. As a result, as the

project develops, additional dangers and unanticipated circumstances could surface, raising the

possibility of disagreements and a partnership breakdown. The most common sources of claims

and disputes were covered by the International Association for Contract and Commercial

Management (IACCM 2011) in its 10th Annual Survey, Top Terms in Negotiation. Table 5

summarizes the key findings. Generally speaking, the owner wishes to transfer as much risk as

feasible to the contractor and take on as little risk as possible. In this instance, the contractor is

only liable for any situations that may develop throughout the project; thus, he is free to raise

the project tender price, A. Peckiene. (2013).

Table 5: Most Sources of Claims and Disputes, IACCM 2011.

Issue % Reported Issue % Reported

Delivery/acceptance 41 Price/charge/price changes 38

Change management 32 Invoices/late payment 30

Performance/guarantees/undertakings 27 Service levels and warranties 27

Payment 25 Responsibilities of the parties 22

Liquidated damages 22 Scope and goals 21

Warranty 16 Limitation of liability 16

Indemnification 14 Service withdrawal or termination 14

Intellectual property 12 Audits/benchmarking 10

Assignment/transfer 8 Dispute resolution 8

Data protection/security 7 Communications and reporting 7

Disputes

Conflicts in industrial projects have become routine in the MENA region. Such a phenomenon

could impede the success of these projects inthe MENA area and slow down development if it

is not controlled well. One of the primary causes of projects failing to meet their goals is the

inherent risk and uncertainty associated with mega industrial undertakings. One of the most

frequent reasons for disagreements and claims in the construction sector is the project parties'

inability to understand their contractual duties. R. Khalef et al., 2021. In general, any country's

economy depends heavily on the building industry. In 2019, ARCADIS reported that the average

cost and duration to resolve construction disputes was $33.0 million, with 17 months being the

average. Claims and disagreements were prevalent in 2016 across most industry sectors, but

Page 15 of 49

68

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

they were particularly prevalent in public sector and social infrastructure projects. According

to the ARCADIS 2017 report, the number of claims and disputes on oil and gas projects is

increasing as the industry becomes more cautious in response to low oil prices. Particularly in

building projects, the MENA area has witnessed a rise in the complexity of contract structures

in recent years. Working relationships, correspondence, and contracts are still not being

fulfilled in a good faith manner. Usually, conflicts arise from the opposing priorities of multiple

parties. These disputes result in the need for more resources, which are wasted and used

needlessly, llankoon et al., 2019. More than 220 claims have been presented for arbitration

during the previous 20 years, according to the Cairo Regional Centre for International and

Commercial Arbitration. Marzouk, M. (2011) developed a survey questionnaire that outlined

forty-four reasons why disagreements arise in the construction industry. The most frequent

reasons for disagreements will guide the owners, contractors, and consultants involved in the

project in resolving these issues. According to Gandhi, M. et al. (2017), ambiguities in

contracts, restricted access, scope modifications, poor documentation, and unforeseen site

conditions are some of the things that lead to disagreements in their research, Hiyassat, M.A.,

et al., 2020 find 62 risk variables that fall into 14 categories in an effort to lower the overall cost

of claims and disputes. Delays in client payments, incorrect contract forms, competitiveness,

and permit approval delays were the top risk factors. Other risk factors were subcontractor

default, poor specifications, fluctuating material prices, disparate construction standards,

design changes, and inadequate implementation. The International Monetary Fund said that

the base case for global growth in 2016 was a moderate 3.2%, mostly consistent with 2015 but

down 0.2% from January 2016. It was anticipated that the recovery would strengthen in 2017

and beyond, mostly due to developing countries as those stressed markets' conditions

progressively return to normal Global Construction Disputes Report 2016 states that there are

significant risks associated with the forecasts, and some market volatility is anticipated. These

factors could have an impact on the volume of construction disputes. This research states that

inadequate contract management is the most frequent reason for disagreements, as shown in

Table 6. According to the research, there has been a global proportionate growth in the usage

of design and contract forms, and one new cause in the rankings is connected to incomplete

design information, which is typically thought to be associated with poor design information

quality. The use of EPC contract formats has caused issues in certain industries.

Table 6: The Most Common Causes of disputes, Global Construction Disputes Report

2016

2015

Rank

CAUSE 2014 Rank

1 Failure to properly administer the contract 1

2 Poorly drafted or incomplete and unsubstantiated claims 2

3 Errors and/or omissions in the contract document 3

4 Incomplete design information or employer requirements (for Design and Build) New

5 Employer/contractor/subcontractor failing to understand and/or comply with its

contractual obligations

4

Even with standard general conditions, contracts would require a significant amount of time to

negotiate and sign if the specific contractual clauses were poorly written or poorly calibrated.

Page 23 of 49

76

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

Fig. 6: Significant Risk Factors Related to Organization Type.

Fig. 6 displayed Important Risk Factors Associated with Organization Type. Figures 7, 8 showed

probability and impact Rating of Risks during Tender Stage. Figures 9, 10 and 11 illustrated

Impact Rating of Reason of Risks by the owner, the Engineer and subcontractors in sequent.

And Finally, Figures 12, 13 and 14 11 illustrated Impact Rating of Reason of Risks related to

resources, Management and Finance in sequent.

Fig.7: Impact Rating of Risks during Tender Stage.

54

52

50

48

46

44

42

40

38

36

34

Contractors Owners All

Respondents

Page 27 of 49

80

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

Fig. 14: Impact Rating of Reasons of Risks related to Finance.

Statistical Analysis of the Survey

For statistical analysis, both qualitative and quantitative data analysis techniques were applied.

The following statistical tools will be used bythe author in her statistical analysis of all the data

that has been gathered, which will be done using IBM's SPSS Ver.25 software (Statistical

Package for the Social Sciences): Questionnaire reliability; Questionnaire structural validity;

Factor ranking and Research-Based Validity ofSurvey.

Reliability of the Questionnaire:

The internal consistency of the factors that have been constructed is measured by reliability.

Utilizing the Cronbach's Alpha Coefficient test within the SPSS software, a reliability analysis

was performed in order to strengthen the validity of the study hypotheses. Any factor with a

corrected item-total correlation value of less than 0.3 would be deemed rejected; Cronbach's

alpha for adequate reliability is 0.8, Kien (2012).The research showed that the Cronbach's alpha

value for all factors was (0.956), which was more than 0.8. Thus, it may be concluded that the

survey was valid and reliable.

Structure Validity of Questionnaire:

The validity of the questionnaire structure, wherein the coefficient of correlation is generated

between the primary fields and all questionnaire fields, will be tested using the Pearson

correlation coefficient through the usage of the (SPSS) program. According to the data,there is

a substantial correlation (Pearson correlation coefficient r > 0.5) and all relationships between

the factors are positive. They are also statistically significant at α = 0.01.

Page 32 of 49

85

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

Delay due to statutory bodies X70 Share Share

Lack of knowledge of existing facilities X38 Share Share

Insufficient FEED documents X7 Mitigate Avoid

Insufficient site investigation X10 Mitigate Avoid

Strong competitors X9 Share Share

Design errors, omissions, and contradiction X34 Mitigate Mitigate

** Correlation is significant at the 0.01 level (2-tailed).

* Correlation is significant at the 0.05 level (2-taile).

Significant Risk Factors and Related Contract Clause/Sub-Clause:

Several Sub-clauses listed in the FIDIC form 2017 Yellow Book should be included in each

balanced contract that is drafted. Suggestions forFIDIC forms are frequently made with the

intention of improving the contract's risk balance. In light of this, the writers will examine a few

driving selective sub-clauses using the data from the earlier research. This paragraph offers a

list of driving selective sub-clauses that the two contracting parties can change based on semi- structured interviews with several project management experts (the second round of

conducted survey) in order to attain risk-related sub-clauses. Any modifications will be

assessed in light of the FIDIC yellow book and the numerical sequence of pertinent sub-clauses.

The significant risk variables and their corresponding modified. Tables 11, 12 show the

important risk factors and the corresponding modified contract clauses. Moreover, table.13

Showed Spearman's Rank Correlation Factor for RII vs FAII Rankings for all Risk Factors within

their Groups. Table 14 also showed Person Correlation of Significant Factors in 2-dimensional

matrix.

Table.11: Significant Risk Factors and the Corresponding Contract Clauses in FIDIC

2017, the Yellow Book.

ID Risk Factor Clause/Sub-Clause

X51 Material delivery doesn't comply with project schedule Sub-Clause 8.3, Sub-Clause 8.8

X35 False progress reports Sub-Clause 8.7

X45 Subcontractor's failure to comply the schedule Sub-Clause 8.3, Sub-Clause 6.9

X55 Procurement problems Sub-Clause 8.8, Sub-Clause 7.7

X6 Unclear responsibility matrix Sub-Clause 4.1, Sub-Clause 1.15

X49 The ability of productivity of subcontractors Sub-Clause 8.3, Sub-Clause 6.9

X15 Indecisive management Sub-Clause 8.3

X5 Change scope of work Sub-Clause 14.1

X43 Lack of coordination between subcontractors Sub-Clause4.4, Sub-Clause 4.5

X16 Lack of procedure to correct errors between owner and

contractor

Sub-Clause 11.1, Sub-Clause 11.4

X2 Insufficient Technical Specifications Sub-Clause 4.1

X31 Compliance Risk (HSE) Sub-Clause 4.8

X69 Late issuance of licenses Sub-Clause 1.13, Sub-Clause 2.2

X28 Defective Materials Sub-Clause 11.5, Sub-Clause 11.9

X17 Frequent changes and/or variations by client. Sub-Clause 4.1

X70 Delay due to statutory bodies Sub-Clause 2.2, Sub-Clause 8.6

X38 Lack of knowledge of existing facilities Sub-Clause 4.1, Sub-Clause 4.6

X7 Insufficient FEED documents Sub-Clause 4.1

X10 Insufficient site investigation Sub-Clause 4.1, Sub-Clause 4.6

Page 33 of 49

86

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

X9 Strong competitors NA

X34 Design errors, omissions and contradiction in documents Sub-Clause 5.1, Sub-Clause 5.3, Sub-clause

5.4

X31 Compliance risks (H&SE) Sub-Clause 1.15 Limitation of Liability

Table 12: Important Risk Factors and Corresponding Modified Clauses as suggestions

for FIDIC 2017(the Yellow Book).

No. Clause/Sub-Clause Risk Factor

1 Standard Sub-Clause 1.13: Compliance with

Laws

• Late issuance of licenses

• Delay due to statutory bodies

2 Standard Sub-Clause 1.15: Limitation of

Liability

• Unclear responsibility matrix

3 Standard Sub-Clause 4.1: Contractor’s

General Obligations

• Unclear responsibility matrix

• Insufficient site investigation

• Insufficient FEED documents

• Insufficient technical specifications

4 Sub-Clause4.4: Subcontractors • Lack of coordination between subcontractors

5 Standard Sub-Clauses 5.1: General Design

Obligations

• Design errors, and contradiction in documents

6 Sub-Clause 8.3: Programme • Indecisive management

• Subcontractor's failure to comply the schedule

• Material delivery doesn't comply with the program

7 Standard Sub-Clause 8.7: Rate of Progress • False progress reports

8 Standard Sub-Clause 8.8: Delay Damage • Material delivery doesn't comply with the program

Procurement problems

9 Standard Sub-Clause 11.3 • Lack of procedure to correct errors between the

employer and the Contractor

10 Extension of Defects Notification Period

Standard Sub-Clause 11.4: Failure to

Remedy Defects

• Defective Materials

11 Standard Sub-Clause 11.10: Unfulfilled

Obligations

• Lack of procedure to correct errors between owner

and contractor Defective Materials

12 Standard Sub-Clause 14.1: The Contract

Price

• Change scope of work

13 Standard Sub-Clause 1.13: Compliance with

Laws

• Late issuance of licenses

• Delay due to statutory bodies

14 Standard Sub-Clause 1.15: Limitation of

Liability

• Unclear responsibility matrix

15 Standard Sub-Clause 4.1: Contractor’s

General Obligations

• Unclear responsibility matrix

• Insufficient site investigation

• Insufficient FEED documents

• Insufficient technical specifications

16 Sub-Clause4.4: Subcontractors • Lack of coordination between subcontractors

17 Standard Sub-Clauses 5.1: General Design

Obligations

• Design errors, and contradiction in documents

18 Sub-Clause 8.3: Programme • Indecisive management

• Subcontractor's failure to comply the schedule

19 Standard Sub-Clause 8.7: Rate of Progress • Material delivery doesn't comply with the program

False progress reports

Page 37 of 49

90

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

Risks related to Finance and Commercial

X62 Interest rate

changes

52.78

49.72

55.28

48.33

50.83

56.11

35

45

24

48

42

22

3

5

2

6

4

1

35.33

32.04

37.31

33.56

32.34

38.19

35

49

27

41

47

25

3

6

2

4

5

1

35.33

32.04

37.31

33.56

32.34

38.19

35

49

27

41

47

25

3

6

X63 Limiting overdraft

facilities

X64 possible cash flow

risks

2

4

X65 Lack of full

knowledge of

taxes/duties

X66 Client financial

credentials

5

X67 General market

conditions

1

Legislations Risks

X68 Change in

legislations/lows

0.70

0.73

0.76

24

9

4

3

2

1

47.78

57.50

54.17

53

17

31

3

1

2

33.58

42.01

41.08

40

13

16

3

X69 Late issuance of

licenses

1

X70 Delay due to

statutory bodies

2

Spearman's correlation

(SPSS)

Correlation Coefficient (FI &FAII)

Sig. (2-tailed)

Correlation Coefficient (RII

&FAII) Sig. (2-tailed)

0.887**

0.000

0.448**

0.000

Table.14: Person Correlation of Significant Factors

Risk

ID

X51 X35 X45 X55 X6 X49 X15 X5 X43 X16 X2 X69 X28 X17 X70 X38 X7 X10 X34

X51 1

X35 0.38 1

X45 0.53 0.40 1

X55 0.50 0.35 1

X6 0.43 0.37 1

X49 0.53 0.81 1

X15 0.31 1 0.61

X5 0.45 0.35 0.33 0.71 0.32 0.31 1

X43 0.57 0.41 0.41 0.47 0.41 0.40 0.30 1

X16 0.37 0.30 0.35 0.30 1

X2 0.33 0.35 0.31 1

X69 0.33 0.34 0.40 1

X28 0.34 0.38 0.38 0.60 0.43 0.39 0.34 0.35 1

X17 0.49 0.50 0.51 0.39 0.31 0.38 0.38 0.38 0.31 1

X70 0.39 0.31 0.36 0.39 0.30 0.35 0.44 1

X38 0.37 0.41 1

X7 0.42 0.34 0.45 0.41 0.32 0.33 0.36 0.48 1

X10 0.41 0.47 0.57 0.45 0.31 0.38 0.47 1

X34 0.32 0.17 0.22 0.23 0.47 0.25 0.24 0.34 0.24 0.10 0.10 0.22 0.27 0.12 0.08 0.18 0.37 0.58 1

**Correlation is highly significant at the 0.01 level (2-tailed).

*. Correlation is significant at the 0.05 level (2-tailed).

Standard Sub-Clause 1.13: Compliance with Laws:

In multi-partner projects, governments and regulatory bodies are the secondary partners; they

have complex contractual relationships with one another both directly and indirectly. Their

goals and approaches are varied, and they are involved in the project at different phases and

Page 39 of 49

92

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

• The Contractor shall in relation to all persons affected or likely to be affected by the

performance of the Work take such steps as are reasonably practicable to ensure their

health, safety and security. The Contractor shall take adequate and effective precautions

in order toprotect the Work, the Contractor’s Personnel, the general public, all other

persons, the environment, the property of the Company and the property of third parties

and to avoid or reduce to a minimum any inconvenience to the public.

Standard Sub-Clause 4.1: Contractor’s General Obligations:

The main reason for the modifications is to make the term "fit for purpose" clearer. This is

because there are risks associated with the contractor's design, implementation strategies, and

supply of materials that meet project specifications. As a result, the purpose of the modification

needs to be made clear in the Employer's Requirements rather than anywhere in the Contract.

The addendum includes affirmation that the design is the contractor's responsibility, that it

conforms to the criteria and guidelines that have been accepted, and that it is free from flaws

that are inherent. The modification also covers the contractor's adherence to environmental,

occupational health, and safetyregulations and safeguards the employer against any hazards

related to the project's operational designs. The modification also serves to protect the

employer from any mistakes or unclear design elements that could compromise the project's

outcome. An additional issue with this subsection is that, in the absence of a set period for

document approval, the employer's delay could impact the schedule for material supply. The

author suggests that the modifications will be written in Italic as follow:

1. The Contractor shall execute and complete the Works in accordance with the

requirements of Contract and with all due skill, care, and safety measures as should be

exercised by a fully qualified, competent and first-class Contractor, fully skilled and

experienced in the design and carrying out of work similar in nature and extent to the

Work. When completed, the Works (or Section or Part or major item of Plant, if any)

shall be fit for the purpose(s) for which they are intended, as defined and described in

the Employer’s Requirements and the standards set out in the Contract (or, where no

purpose(s) are so defined and described, fit for their ordinary purpose(s)).

2. The Contractor shall at its own cost provide

• the Plant all Contractor Provided Items and Equipment (and spare parts, if any)

• the Contractor’s Documents specified in the Employer’s Requirements,

• All Contractor’s Personnel, Goods, consumables and other things and services,

whether of a temporary or permanent nature, required to fulfil the Contractor’s

obligations under the Contract.

3. The Works shall include any work which is necessary to satisfy the Employer’s

Requirements, Contractor’s Proposal and Schedules, oris implied by the Contract, and

all works which (although not mentioned in the Contract) are necessary for stability or

for the completion,or safe and proper operation, of the Works.

4. The Contractor shall be responsible for:

• the adequacy; stability and safety of all the Contractor’s operations and activities, of

all methods of construction and of all the Works;

• the engagement and management of Sub-Contractors in connection with the Work;

• the timely provision of all items referred to in the Contract including the timely

Page 42 of 49

95

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

provide the name, address, full details, and pertinent expertise of each prospective

designer or design subcontractor to the Engineer for approval.

• The Contractor warrants that the Contractor, the Contractor’s designers and design

Subcontractors are adequately financed, competent, qualified and fully experienced

in the design, procurement, fabrication, construction, testing, pre-commissioning and

commissioning of projects of a similar scope, complexity, size and technical

sophistication as the Work and that it possesses the high level of skill and expertise

commensurate with that experience.

• The Contractor covenants that the Work shall be free from inherent or Latent Defects

whether in design, engineering, workmanshipor materials and shall be free of errors

and omissions in design and engineering.

• The Employer is relying upon the skill, judgement and expertise of the Contractor in

the performance of the Work and the co- ordination and planning thereof including

without limitation the preparation and execution of the Programme.

• The Contractor undertakes that the designers and design Subcontractors shall be

available to attend discussions with the Engineer and/or the Employer at all

reasonable times (on or off the Site), until the issue of the Performance Certificate.

• Promptly after receiving a Notice under Sub-Clause 8.1 [Commencement of Works],

the Contractor shall scrutinise the Employer’s Requirements (including design

criteria and calculations, if any). If the Contractor discovers any error, fault or other

defect in the Employer’s Requirements, Sub-Clause 1.9 [Errors in the Employer’s

Requirements] shall apply (unless it is an error in the items of reference specified in

the Employer’s Requirements, in which case Sub-Clause 4.7 [Setting Out] shall apply).

Regretfully, it frequently happens that the intended objectives are unclear or may never be

determined. While most Contractors will find this unsettling, some Employers and consulting

engineers are unable to fully benefit from Sub-clause 5.1. One of the most significant problems

that both the employer and the contractor are likely to face at the same time is risk

management. As a result, it's critical to take a proactive approach to reducing these risks by

establishing stringent guidelines that require the contractor to exercise extreme caution when

choosing the team responsible for design preparation, being aware of the project's primary goal

and the nature of the work, and examining the underlying principles that will guide the creation

of the designs. These terms could shield the contractor directly by establishing.

CONCLUSION

This study finds that a cooperative connection between the two parties to the contract can

ensure more satisfied project results by keeping aneye out for key risk factors and putting risk

mitigation measures into place through the provisions of the contract. The literature analysis

andrecommendations from experts were used to identify the main risk factors for industrial

projects. To ascertain the most important risk factors influencing the project objectives, a

questionnaire was created and sent to a number of project management specialists. The

findings demonstrated that there is an issue with how risks in large-scale industrial

undertakings are divided up among different stakeholders. According to the study, risk during

tender accounted for 29% of important risk variables. This suggests that these risks may be

prevented bysuitably modifying the contract clauses to ensure that the risks are allocated in a

Page 43 of 49

96

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

transparent manner. Although design flaws, faulty material, and compliance risks (H&SE)

accounted for 25% of significant risk factors, these risks can be reduced by making the

necessary changes to contract terms for procurement, design review, and quality control, which

permit the sharing of these kinds of risks. The remaining risk factors were caused by

subcontractor issues and indecisive management; these threats can be reduced by including

provisions for the owner to monitor the project's implementation progress in order to develop

solutions for any obstacles that arise on the fly. FIDIC forms undoubtedly offer a comprehensive

starting point for the writing of industrial project contracts, but they also include a number of

clauses that employers and contractors should carefully review for the significant

consequences that may develop later. In summary, the parties should work to reach a

compromise that meets their needs for both reasonable flexibility on the part of the employers

and a balance of risks for the contractors. This will allow the contractors to adjust their

compensation to the level of presumed risk, and the employers to modify their contractual

obligations to reflect changes in project conditions over time. This equilibrium will most likely

benefit the project asa whole, positively affecting both the parties' contractual relationship and

the project's completion.

Data Availability Statement

All data, models, and code generated or used during the study appear in the submitted article.

References

Abdullah, M.S., Alaloul, W.S., Liew, M.S. and Mohammed, B.S., 2018. Delays and cost overruns cause during

construction of palm oil refineryprojects. In MATEC Web of Conferences (Vol. 203, p. 02004). EDP Sciences.

Adam, A., Josephson, P.E. and Lindahl, G., 2015. Implications of cost overruns and time delays on major public

construction projects. In Proceedings of the 19th International Symposium on Advancement of Construction

Management and Real Estate (pp. 747-758). Springer, Berlin,Heidelberg.

ARCADIS, 2017, 2019, Construction disputes in the Middle East being resolved quicker than before.

Assaad, R., A. Elsayegh, G. Ali, M. Abdul Nabi, and I. H. El-adaway. 2020b. “Back-to-back relationship under

standard subcontract agreements:Comparative study.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (3): 04520020.

https://doi.org/10.1061/(ASCE)LA.1943-4170 .0000406.

Assaad, R., and I. H. El-adaway. 2020c. “Enhancing the knowledge of construction business failure: A social

network analysis approach.” J. Constr.

Eng. Manage. 146 (6): 04020052. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001831.

Bidua, A.K., 2018, November. Use of FIDIC 2017 as Standard Form of Contract for EPC Projects in Oil and Gas

Industry. In Abu Dhabi International Petroleum Exhibition & Conference. Society of Petroleum Engineers.

Boateng, P., Chen, Z. and Ogunlana, S.O., 2015. An Analytical Network Process model for risks prioritization in

megaprojects. International Journal of Project Management, 33(8), pp.1795-1811.

Chang, C.Y., 2014. Principal-agent model of risk allocation in construction contracts and its critique. Journal of

Construction Engineering andManagement, 140(1), p.04013032.

Cummins, T., 2015. Strategic contracting as a source of organizational success. Journal of Strategic Contracting

and Negotiation, 1(1), pp.7-14. Dastyar, B., Esfahani, A.F., Askarifard, M. and Abbasi, A.M., 2018. Identification,

Page 44 of 49

97

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

Prioritization and Management of Construction Project Claims. Journal of Engineering, Project & Production

Management, 8(2).

Eskander, R.F.A., 2018. Risk assessment influencing factors for Arabian construction projects using analytic

hierarchy process. Alexandriaengineering journal, 57(4), pp.4207-4218.

Gamal El-Din Nassar. Claims, Disputes and Arbitration. According to FIDIC Conditions of Contract for Civil,

Mechanical, Electrical, Construction,Design/Build & Turkey, EPC & Short Form. Published by FIDIC (From 1953

up to 1999)

Gandhi, M. and Dey, A., 2017. Avoiding an arbitration dispute. International Journal of Innovative Research in

Advanced Engineering, (09).Haapio, H. and Siedel, G.J., 2017. A short guide to contract risk. Routledge.

Haidar, A., 2011. Global claims in construction. Springer Science & Business Media.

Hiyassat, M.A., Alkasagi, F., El-Mashaleh, M. and Sweis, G.J., 2020. Risk allocation in public construction projects:

the case of Jordan. InternationalJournal of Construction Management, pp.1-11.

Hosseinian, S.M. and Carmichael, D.G., 2013. Optimal incentive contract with risk-neutral contractor. Journal of

Construction Engineering andManagement, 139(8), pp.899-909.

Hui, S. and Bai-zhou, H., 2013, November. Revision of the construction project contract model text in China. In

2013 6th International Conference on Information Management, Innovation Management and Industrial

Engineering (Vol. 2, pp. 595-599). IEEE.

IACCM 2014 International Association for Contract and Commercial Management. Commercial Excellence: Ten

Pitfalls to Avoid in Contracting.www.iaccm.com

IACCM 2014 International Association for Contract and Commercial Management. Commercial Excellence: Ten

Pitfalls to Avoid in Contracting.www.iaccm.com

Illankoon, I.M.C.S., Tam, V.W., Le, K.N. and Ranadewa, K.A.T.O., 2019. Causes of disputes, factors affecting dispute

resolution and effectivealternative dispute resolution for Sri Lankan construction industry. International Journal

of Construction Management, pp.1-11.

John E Miller, 2014. Managing contractual risk issues in commercial contracts. Contract Management, January

2014, pp.26-39Keane, P.J. and Caletka, A.F., 2015. Delay analysis in construction contracts. Wiley Blackwell.

Khalef, R., El-adaway, I.H., Assaad, R. and Kieta, N., 2021. Contract risk management: A comparative study of risk

allocation in exculpatory clausesand their legal treatment. Journal of Legal Affairs and Dispute Resolution in

Engineering and Construction, 13(1), p.04520036.

Khazaeni, G., Khanzadi, M. and Afshar, A., 2012. Fuzzy adaptive decision-making model for selection balanced

risk allocation. International Journalof Project Management, 30(4), pp.511-522.

Komurlu, R. and Arditi, D., 2017. The role of general conditions relative to claims and disputes in building

construction contracts. New Arch-International Journal of Contemporary Architecture, 4(2), pp.27-36.

Kumar, R.K. and Jegan, G.S., 2019. Risk Management of Contracts in Construction Projects. Risk Management,

6(04).

Li, Y., Wang, X. and Wang, Y., 2017. Using bargaining game theory for risk allocation of public-private partnership

projects: Insights from different alternating offer sequences of participants. Journal of Construction Engineering

and Management, 143(3), p.04016102.

Page 45 of 49

98

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

Li, Y., Wang, X. and Wang, Y., 2017. Using bargaining game theory for risk allocation of public-private partnership

projects: Insights from different alternating offer sequences of participants. Journal of Construction Engineering

and Management, 143(3), p.04016102.

Lim, B.T. and Loosemore, M., 2017. The effect of inter-organizational justice perceptions on organizational

citizenship behaviors in constructionprojects. International Journal of Project Management, 35(2), pp.95-106.

Lu, W., Zhang, L. and Pan, J., 2015. Identification and analyses of hidden transaction costs in project dispute

resolutions. International journal ofproject management, 33(3), pp.711-718.

Mahamid, I., 2013. Contributors to schedule delays in public construction projects in Saudi Arabia: owners'

perspective. Journal of ConstructionProject Management and Innovation, 3(2), pp.608-619.

McCord, M., Davis, P. T., Haran, M., & Rodgers, W. J.(2015). Understanding delays in housing construction:

Evidence from Northern Ireland. Journal of Financial Management of Property and Construction, 20(3), 286–319.

Melese, Y., Lumbreras, S., Ramos, A., Stikkelman, R. and Herder, P., 2017. Cooperation under uncertainty:

Assessing the value of risk sharing anddetermining the optimal risk-sharing rule for agents with pre-existing

business and diverging risk attitudes. International Journal of Project Management, 35(3), pp.530-540.

Mentis, M., 2015. Managing project risks and uncertainties. Forest ecosystems, 2(1), p.2.

Mohammadi, S. and Birgonul, M.T., 2016. Preventing claims in green construction projects through investigating

the components of contractual andlegal risks. Journal of cleaner production, 139, pp.1078-1084.

Mona Abdel Hamid Hassanen, Ahmed Mohammed Abdelalim. Risk Identification and Assessment of Mega

Industrial Projects in Egypt.

International Journal of Management and Commerce Innovation (IJMCI). Vol 10 Issue 1 April 2022-September

2022

Nasirzadeh, F., Khanzadi, M., and Rezaie, M. (2014). “Dynamic modeling of the quantitative risk allocation in

construction projects.” Int. J. ProjectManagement. 32(3), 442–451.

Nasirzadeh, F., Mazandaran Zadeh, H. and Rouhparvar, M., 2016. Quantitative risk allocation in construction

projects using cooperative-bargaininggame theory. International Journal of Civil Engineering, 14(3), pp.161-170.

Nguyen, D.A., Garvin, M.J. and Gonzalez, E.E., 2018. Risk allocation in US public-private partnership highway

project contracts. Journal ofConstruction Engineering and Management, 144(5), p.04018017.

Nguyen, P.T. and Nguyen, P.C., 2020. Risk Management in Engineering and Construction. Engineering,

Technology & Applied Science Research,10(1), pp.5237-5241.

Peckiene, A., Komarovska, A. and Ustinovicius, L., 2013. Overview of risk allocation between construction parties.

Procedia Engineering, 57,pp.889-894.

Peter Fogh, Niklas Korsgaard Christensen, Anne-Sophie Truelsen, 2017. Major Changes in FIDIC Red, Yellow and

Silver Book. PP.1-6 Pham, L.H. and Hadikusumo, H., 2014. Schedule delays in engineering, procurement, and

construction petrochemical projects in Vietnam: A qualitative research study. International Journal of energy

sector management.

Prasad, K.V., Vasugi, V., Venkatesan, R. and Bhat, N.S., 2019. Critical causes of time overrun in Indian construction

projects and mitigationmeasures. International Journal of Construction Education and Research, 15(3), pp.216-

238.

Page 46 of 49

99

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

Project Management Institute PMI. (2017). A Guide to The Project Management Body of Knowledge (PMBOK- Guide) - Sixth version,Pennsylvania, USA: Project Management Institute, Inc.

Project Management Institute, A guide to the project management

Rameezdeen, R. and Rodrigo, A., 2014. Modifications to standard forms of contract: The impact on readability.

Australasian Journal of Construction Economics and Building, The, 14(2), pp.31-40.

Saaidin, S., Endut, I.R., Samah, S.A.A. and Ridzuan, A.R.M., 2017. Stakeholder’s Perspective on Risks Allocation in

Design and Build Projects inMalaysia. In MATEC Web of Conferences (Vol. 103, p. 03009). EDP Sciences.

Sadek, S. and Kulatunga, U., 2013. An overview of standard contractual forms modifications in the construction

industry-the Middle East. Shafik, N., Qodsi, S., Serag, E. and Helmi, M., 2016. Application of FIDIC contracts under

the Egyptian civil code. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 8(3),

p.04516004.

Solimene, F., 2014. Use of FIDIC forms in the oil and gas construction sector and possible amendments to the

Yellow and Silver Books. The Journalof World Energy Law & Business, 7(6), pp.558-571.

Subcommittee TI of the International Bar Association, 2013, Standard form of construction contracts

Suprapto, M., Bakker, H.L., Mooi, H.G. and Hertogh, M.J., 2016. How do contract types and incentives matter to

project performance? InternationalJournal of Project Management, 34(6), pp.1071-1087.

Tang, Y., Chen, Y., Hua, Y. and Fu, Y., 2020. Impacts of risk allocation on conflict negotiation costs in construction

projects: Does managerialcontrol matter? International Journal of Project Management, 38(3), pp.188-199.

Tataretaghi, F. (2011). An Overview of Comparison between Parties of Construction Contracts in Malaysia.

European Journal of Scientific Research,49 (30): 415-420.

Tembo-Silungwe, C.K. and Khatleli, N., 2020. Development of risk misallocation causal networks using

interpretive judgement in the constructionindustry. International Journal of Construction Management, pp.1-15.

Van Weele, A., 2014. International contracting: Contract management in complex construction projects. World

Scientific.

Walsh, K.P., 2017. Identifying and mitigating the risks created by problematic clauses in construction contracts.

Journal of Legal Affairs and DisputeResolution in Engineering and Construction, 9(3), p.03717001.

Wan, S., Ding, G., Runeson, G., Er, M. and Liu, Y., 2019, June. A Dynamic Model of Risk Allocation of Energy

Efficiency Retrofits under Energy Performance Contract for Office Buildings in China. In Abstract Proceedings of

2019 International Conference on Resource Sustainability-Cities(acres Cities).

Wang, Y., Chen, Y., Wang, W. and Tang, Y., 2019. Differentiating two types of learning in contract design: Evidence

from the construction industry.

Scandinavian Journal of Management, 35(1), pp.1-11.

Youssef, A., Osman, H., Georgy, M. and Yehia, N., 2018. Semantic risk assessment for ad hoc and amended

standard forms of constructioncontracts. Journal of Legal Affairs and Dispute Resolution in Engineering and

Construction, 10(2), p.04518002.

Zavadskas, E.K., Turskis, Z. and Tamošaitiene, J., 2010. Risk assessment of construction projects. Journal of civil

engineering and management,16(1), pp.33-46.

Page 47 of 49

100

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

Zhang, L. and Qian, Q., 2017. How mediated power affects opportunism in owner–contractor relationships: The

role of risk perceptions. InternationalJournal of Project Management, 35(3), pp.516-529.

Zhang, L. and Qian, Q., 2017. How mediated power affects opportunism in owner–contractor relationships: The

role of risk perceptions. InternationalJournal of Project Management, 35(3), pp.516-529.

Abdelalim, A.M., 2019. “Risks Affecting the Delivery of Construction Projects in Egypt: Identifying, Assessing and

Response”. In Project Management and BIM for Sustainable Modern Cities: Proceedings of the 2nd GeoMEast

International Congress and Exhibition on SustainableCivil Infrastructures, Egypt 2018–The Official International

Congress of the Soil-Structure Interaction Group in Egypt (SSIGE) (pp. 125-154).Springer International

Publishing.

Abd El-Karim, M.S.B.A., Mosa El Nawawy, O.A. and Abdelalim, A.M., 2017. Identification and assessment of risk

factors affecting constructionprojects. HBRC journal, 13(2), pp.202-216.

Medhat, W., Abdelkhalek, H. and Abdelalim, A.M., 2023. “A Comparative Study of the International Construction

Contract (FIDIC Red Book 1999)and the Domestic Contract in Egypt (the Administrative Law 182 for the year

2018)”, International Journal of Management and Commerce Innovations, Vol.11, Issue.1, pp.10-23.

Abd El-Hamid, M.S, Farag, S., Abdelalim, A.M., 2023, “Construction Contracts’ Pricing according to Contractual

Provisions and Risk Allocation”,International Journal of Civil and Structural Engineering Research ISSN 2348-

7607, Vol.11, Issue.1, pp.11-38.

Yousri, Elhosin, Ahmed El Badawy Sayed, Moataz A. M. Farag, and Ahmed Mohammed Abdelalim. 2023. "Risk

Identification of BuildingConstruction Projects in Egypt" Buildings 13, no. 4: 1084.

https://doi.org/10.3390/buildings13041084.

Sherif Awad, Samir Gad, Abdelalim, A.M, 2023, “Critical Failure of Construction Projects and Their Remedial

Actions from the Perspective of Applying Total Quality Management”, International Journal of Engineering,

Management and Humanities (IJEMH), Vol.4, Issue.1, 147-167.

Khedr, R. and Abdelalim, A.M., 2021, “The Impact of Strategic Management on Projects Performance of

Construction Firms in Egypt”, InternationalJournal of Management and Commerce Innovations ISSN 2348-7585,

Vol. 9, Issue 2, pp.: (202-211).

Khedr, R. and Abdelalim, A.M., 2021, “Predictors for the Success and Survival of Construction Firms in Egypt”,

International Journal ofManagement and Commerce Innovations ISSN 2348-7585 (Online), Vol. 9, Issue 2, pp.:

(192-201).

Zou, X., & Vu, H. L. (2019). Mapping the knowledge domain of road safety studies: A scientometric analysis.

Accident Analysis and Prevention 132(2019) 1052.

Cochran, W.G., 1977. Sampling techniques. John Wiley & Sons.

Naoum, S., Mustapha, F. H., "Factors influencing the effectiveness of construction site managers." International

journal of project management 16, no. 1 (1998): 1-8. Mustapha, F. H., and S. Naoum. "Factors influencing the

effectiveness of construction site managers." International journal ofproject management 16, no. 1 (1998): 1-8.

Odeh, A.M. and Battaineh, H.T., 2002. Causes of construction delay: traditional contracts. International journal of

project management, 20(1), pp.67-73

Al-Bahi, M.F., 1979. Statistical Psychology. Measuring the Human Mind, Cairo: Dar Al-Fikr Al-Arabi.

Page 48 of 49

101

Abdelalim, A. M., Hassanen, M. A., & ElSamadony, A. (2024). Risk Allocation and Sharing in Mega Industrial Projects from the Perspective of the New

Yellow Book -FIDIC-2017 to Approach a Balanced Construction Contract. Transactions on Engineering and Computing Sciences, 12(1). 54-102.

URL: http://dx.doi.org/10.14738/tecs.121.16260

Abd El-Hamid, S., Abdelalim, A.M, 2021, “A Proposed System for Prequalification of Construction Companies &

Subcontractors for Projects inEgypt”, International Journal of Management and Commerce Innovations ISSN

2348-7585, Vol. 9, Issue 2, pp.: 290-304.

Abdelalim, A.M., Elbeltagi, E. and Mekky, A.A., 2019. Factors affecting productivity and improvement in building

construction sites, International Journal of Productivity and Quality Management, 27(4), pp.464-494.

Abdelalim, A.M., 2018, “IRVQM, Integrated Approach for Risk, Value and Quality Management in Construction

Projects; Methodology and Practice”, the 2nd International Conference of Sustainable Construction and Project

Management, Sustainable Infrastructure and Transportationfor Future cities, ICSCPM-18, 16-18 December, 2018,

Aswan, Egypt.

Amr Afifi, El. Samadony, A and Abdelalim, A.M., 2020, “Risk Response Planning for Top Risks Affecting Schedule

and Cost of Mega ConstructionProjects in Egypt”, International Journal of Civil and Structural Engineering

Research ISSN 2348-7607 (Online) Vol. 8, Issue 1, pp.: 79-93.

Amr Afifi, El. Samadony, A and Abdelalim, A.M., 2020, “A Proposed Methodology for Managing Risks in

Construction Industry in EGYPT”,International Journal of Civil and Structural Engineering Research ISSN 2348-

7607, Vol. 8, Issue 1, pp.: 63-78.

Abdelalim, A.M., El Nawawy, O.A. and Bassiony, M.S., 2016. ’Decision Supporting System for Risk Assessment in

Construction Projects: AHP-Simulation Based. IPASJ International Journal of Computer Science (IIJCS), 4(5),

pp.22-36.

Abdelalim, A.M., Mahmoud Eldesouky, 2021, “Evaluating Contracting Companies According to Quality

Management System Requirements inConstruction Projects”, International Journal of Engineering, Management

and Humanities (IJEMH), Vol. 2, Issue 3, pp.: 158-169.

Abdelalim, A.M., Khalil, E.B. and Saif, A.A., 2021, “The Effect of Using the Value Engineering Approach in

Enhancing the Role of Consulting Firms in the Construction Industry in Egypt”. International Journal of Advanced

Research in Science, Engineering and Technology, ISSN: 2350-0328 Vol. 8, Issue 2, pp. 16531-16539.

Ahmed Mohammed Abdelalim, Rizk Elimam A. Youni, Hesham Abdelkhalek, 2022, “Project Risk Management

during Construction Stage According to International contract (FIDIC)”, Al-azhar University Research Magazine,

Civil Engineering (CERM), Vol.10, Issue.2, pp.76-93.

Abd-Elhamed, A., Amin, H.E. and Abdelalim, A.M.,2020, “Integration of Design Optimality and Design Quality of

RC buildings from the perspective of Value Engineering”, International Journal of Civil and Structural

Engineering Research ISSN 2348-7607 (Online) Vol. 8, Issue 1,pp.:105-116

Zena A. Fadhel, El. Samadony and Abdelalim, A.M, 2020, “Studying the Applicability of Public Private Sector

Partnership in the Reconstruction Projects in Iraq “International Journal of Civil and Structural Engineering

Research ISSN 2348-7607, Vol. 8, Issue 1, pp.: 137-150.

Khaled Al-Barghouth, El. Samadony, A. And Abdelalim, A.M, 2016, “The Applicability of Public Private Sector

Partnership (PPP) in the futuristic Reconstruction in Syria”, The Engineering Sciences Magazine- Faculty of

Engineering at Mataria- Helwan University, Vol.148, Issue.1.

Abdel-Alim, A.M. and Said, S.O.M., 2021, “Dynamic Labour Tracking System in Construction Project Using BIM

Technology”, InternationalJournal of Civil and Structural Engineering Research ISSN 2348-7607 (Online) Vol. 9,

Issue 1, pp.: 10-20.

Page 49 of 49

102

Transactions on Engineering and Computing Sciences (TECS) Vol 12, Issue 1, February - 2024

Services for Science and Education – United Kingdom

Abd-Elhamed, A., Amin, H.E. and Abdelalim, A.M.,2020, “Integration of Design Optimality and Design Quality of

RC buildings from the perspective of Value Engineering”, International Journal of Civil and Structural

Engineering Research ISSN 2348-7607 (Online) Vol. 8, Issue 1,pp.:105-116.

Abdelalim, A.M., El. Samadony, A. and Alaa Al-Harouny, 2016, “Risk Assessment and Mitigation for Construction

Projects in Egypt”, the International Conference of Sustainable Construction and Project Management, ICSCPM- 16, 29-31March, 2016, Aswan, Egypt.

Abdelalim, A.M. and Said, S.O.M., 2021.” Theoretical Understanding of Indoor/Outdoor Tracking Systems in the

Construction Industry”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607

(Online) Vol. 9, Issue 1, pp: (30-36), Month: April 2021.

Abdelalim, A.M. and Said, S.O.M., 2021. “Dynamic labour tracking system in construction project using BIM

technology”, International Journal of Civil and Structural Engineering Research ISSN 2348-7607 (Online), Vol. 9,

Issue 1, pp: (10-20), Month: April 2021 - September 2021.

Abdelalim, A.M. and Abo. elsaud, Y., 2019. Integrating BIM-based simulation technique for sustainable building

design. In Project Management andBIM for Sustainable Modern Cities: Proceedings of the 2nd GeoMEast

International Congress and Exhibition on Sustainable Civil

Infrastructures, Egypt 2018–The Official International Congress of the Soil-Structure Interaction Group in Egypt

(SSIGE) (pp. 209-238).Springer International Publishing.

Abdelalim, A.M., El-Kholy, A., 2016. A comparative study for fuzzy ranking methods in determining economic life

of equipment. International Journal of Construction Engineering and Management, 5(2), pp.42-54.

Abdelalim, A.M., El Nawawy, O.A. and Bassiony, M.S., 2016. ’Decision Supporting System for Risk Assessment in

Construction Projects: AHP-Simulation Based. IPASJ International Journal of Computer Science (IIJCS), 4(5),

pp.22-36.